How Long Do I Have to Make a Claim? 

In the legal system of England and Wales, the right to bring a claim for a breach of contract is not indefinite. The law imposes strict time limits, known as “limitation periods,” within which a claimant must initiate formal court proceedings. These rules are primarily governed by the Limitation Act 1980. If you fail to bring your claim within the specified timeframe, your claim becomes “statute-barred,” which provides the defendant with a complete defence and effectively extinguishes your right to a legal remedy.

The General Limitation Periods

The law distinguishes between two primary forms of contract when setting time limits.

Simple Contracts: The Six-Year Rule This is the most common limitation period and applies to what are known as “simple contracts.” This category encompasses the vast majority of agreements, including those that are:

  • Written: A standard commercial agreement signed by both parties.
  • Oral: A verbal agreement that can be proven to exist.
  • Implied by Conduct: An agreement formed through the actions of the parties.
  • For any breach of a simple contract, Section 5 of the Limitation Act 1980 stipulates that a claimant has six years to commence legal action.
  • Contracts Executed as a Deed: The Twelve-Year Rule A deed is a more formal and solemn type of legal document. For an instrument to be a deed, it must be in writing and make it clear on its face that it is intended to be a deed. It must also be validly executed, which typically means it is signed in the presence of a witness who attests to the signature.
  • Due to their enhanced formality, contracts executed as deeds are afforded a longer limitation period. Section 8 of the Limitation Act 1980 provides that a claim for a breach of an obligation contained in a deed can be brought within twelve years. Deeds are commonly used for significant transactions such as property conveyancing, mortgages, and certain high-value commercial guarantees.

When Does the Limitation Clock Start Ticking?

  • This is a critical and often misunderstood aspect of the law. The limitation period does not begin from the date the contract was signed, nor does it begin from the date you discovered the breach. The clock starts running from the date on which the cause of action accrues, which, in the context of a contract breach, is the date the breach actually occurred.
  • This principle can have harsh consequences, as the time limit may be well underway, or even expired, before the innocent party is even aware that something is wrong.

Illustrative Example: A construction company is contracted to build a commercial warehouse and completes the project in October 2025. The contract specifies a certain grade of steel for the roof trusses. The company, in breach of contract, uses a lower-grade, cheaper steel. This defect is not immediately apparent. In December 2028, the roof begins to sag, and an expert inspection reveals the use of the substandard steel.

In this scenario, the breach of contract occurred in October 2025 when the wrong materials were incorporated into the building. The six-year limitation period started then. It did not start in December 2028 when the defect was discovered. Therefore, the building owner would have until October 2031 to issue a claim.

Exceptions and Postponement of the Limitation Period

  • While the rule on the start date is strict, the Limitation Act 1980 contains important exceptions that can postpone the commencement of the limitation period in certain circumstances of wrongdoing or disability.
  • Fraud, Concealment, or Mistake Section 32 of the Limitation Act is a crucial provision designed to prevent a defendant from benefiting from their own dishonesty. It states that where a claim is based upon the fraud of the defendant, or where any fact relevant to the claimant’s right of action has been deliberately concealed by the defendant, the limitation period will not begin to run until the claimant has discovered the fraud or concealment, or could have discovered it with reasonable diligence.
  • In our construction example, if the building owner could prove that the contractor knowingly used the wrong steel and then actively took steps to hide that fact (e.g., by falsifying supply records), the six-year period would not start until the owner discovered (or could have reasonably discovered) the concealment in December 2028.
  • Disability If the person entitled to bring a claim is under a “disability” (defined as being a minor under 18 or lacking mental capacity) at the time the cause of action accrues, the limitation period is paused. The clock will only start to run from the date the disability ceases (i.e., when the claimant turns 18 or regains capacity).
  • “Standstill” Agreements In commercial disputes, it is common for parties to enter into a “standstill agreement.” This is a contractual agreement to suspend the running of the limitation period, usually while the parties engage in negotiations or alternative dispute resolution in an attempt to settle the matter without resorting to litigation.

The Consequence of Missing the Deadline: “Statute-Barred”

  • The consequence of failing to issue a claim within the prescribed time limit is final and severe. The claim becomes statute-barred. This does not mean the underlying obligation ceases to exist, but it does mean that the claimant has lost the right to enforce it through the courts.
  • If you bring a claim after the limitation period has expired, the defendant can simply raise the Limitation Act 1980 as a defence. This provides them with a complete and unassailable defence, and the court will be compelled to dismiss your claim. For this reason, it is imperative to seek legal advice as soon as you suspect a breach of contract has occurred to ensure your legal rights are preserved.

Latest FAQs

Search Icon
Toggle Icon
Is Mediation Compulsory Before Taking a Property Dispute to Court? 
Mediation in the legal system of England and Wales is a process of Alternative Dispute Resolution (ADR) where a neutral, independent third party the mediator assists disputing parties in reaching a mutually acceptable settlement. Unlike a judge in...Read More
Toggle Icon
What Are the Legal Remedies for a Breach of Lease Agreement?
A breach of a lease agreement occurs when either the landlord or the tenant fails to perform the obligations, conditions, or covenants set out in the leasehold contract. In the legal jurisdiction of England and...Read More
Toggle Icon
Can I Claim Compensation for Encroachment on My Registered Land? 
Encroachment on registered land is a form of trespass to land occurring when a neighbor or third party constructs a building, fence, or other structure that extends across the boundary line and onto your...Read More
Toggle Icon
How Do I Resolve a Dispute Over a Shared Property Driveway?
A shared property driveway in England and Wales is a legal arrangement where two or more parties possess the right to use a specific strip of land for access, typically to reach a garage...Read More
Toggle Icon
What Is the Pre-Action Protocol for Residential Property Disputes? 
The Pre-Action Protocol in the legal system of England and Wales refers to a set of procedural requirements that parties must satisfy before initiating formal court proceedings in the Civil Courts. Established under the Civil Procedure Rules (CPR),...Read More

Search

Find articles, FAQs, lawyers, and more

Press Enter to search or ESC to close

Secret Link